Background

As part of the Rio Tinto Power Station Upgrade, Valmec was contracted to supply, fabricate, construct and install the pipeline facilities (inlet, MLV and delivery stations) to convey natural gas from the Goldfields Gas Pipeline (GGP) to the West Angelas Power Station (WAPPL).

Client

OSD/Mondelphous KT

Challenges

The works required to be completed involved three (3) separate remote work fronts spread over approximately 100km.

Advantages

Experience in remote location logistics management and a flexible workforce that are prepared to be accommodated in temporary camp style accommodation allowed a cost effective solution at a time of peak construction activity in Western Australia.