Harvest 2
Harvest 1

Harvest Lakes Stages 11A and 12B

Perth, Western Australia

Background

This Landcorp project was consulted on by consulting engineers Tabec, located in the quickly developing south metro area of Atwell, Perth. The project involved 2 phases for Stage 11, of which the works of some 60 lots required all site works to be completed. These included bulk earthworks, retaining walls, roadworks, stormwater drainage, sewerage, water reticulation and services.

Client

LandCorp

Challenges

2 significant contributions to the works included importation of sand fill to the site. Some 13,200m3 of fill was required to be imported in the initial program. This
placed emphasis on the initial program so measures were taken to source and supply the sand prior to mobilising to site. The second significant factor was the construction of retaining walls on the project. Early procurement and emphasis on programming were paramount to the project’s success.

Advantages

The project team were well experienced and ran the project to a tight budget. As a result the project ran on time and within budget.